Project Schedule

The Detail Design and Class Environmental Assessment (EA) Study for the replacement of the Highway 401 / Wilson Road overpass (Contract A) and the reconstruction of the Highway 401 Bloor Street / Harmony Road interchange (Contract B) commenced in March 2021.

Construction for Contract A commenced in Fall 2024 and is expected to be completed in 2027.  The timeline for Contract B construction is still being confirmed and will be coordinated with the Region of Durham’s planned realignment and widening of Bloor Street from east of Harmony Road to Grandview Street. The construction of Contract B is anticipated in 2028 as per the Ontario Highways Program.

Skip to content
Privacy Overview
Abstract logo illustration with a curved blue shape and a yellow stripe, symbolizing a highway or road.

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

3rd Party Cookies

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.